(Sunday, October 7, 2018)
16:38
The CEO of Pars Oil and Gas Company (POGC) said Iran's natural gas production from the supergiant South Pars Gas Field will increase by 100 million cubic meters by the end of the current calendar year to Mach 2019.
According to
POGC, Mohammad Meshkinfam said two gas sweetening trains of phase 13 refinery
was being fed by the gas recovered from phases 6 to 8 of the gas field, adding
two other trains of the refinery would come on-stream by November.
He also said
that the phase's production would reach 56 mcm/d during winter.
The official
stated that the third train of phases 22 to 24 refinery would also come online
by November, adding the first train of the phases' onshore refinery was
operating and its second sweetening train would be presently operational.
He said that
the third sweetening train of the refinery was planned to come online by
November and it last train would become operational by March 2019, Shana wrote.
Meshkinfam
further added that by November three offshore platforms would become
operational in South Pars which would add 84 mcm/d to the field's total gas
production capacity.
He went on
to add that the third platform of phase 14 of the joint gas field would come
on-stream during winter with 14.1 mcm/d of sour gas production capacity.
The phase's
productivity would reach 28 mcm/d by November, he added. Inauguration of the
third platform of the phase would bring its total production capacity to 42
mcm/d.
Follow us on
Twitter @ SouthPSEEZ