Launching Pre-Commissioning of the Ammonia Unit at the Beginning of March

(Sunday, January 22, 2023) 11:28

The Deputy Director of Planning of the Persian Gulf Petrochemical Industries announced the start of the pre-commissioning of the ammonia unit by early March, 2023

The Vice President of Planning and Business Development of Persian Gulf Petrochemical Industries Company, referring to the 86% progress of the construction of Urea and Ammonia Petrochemical Units, said: The pre-launch steps of this project will take place on March 1st, 2023.

According to Shana, citing the Persian Gulf Petrochemical Industries Company, Hassan Neshanzadeh visited the projects of the Persian Gulf Petrochemical Industries Group in Asalouyeh, stating that determining the task of the construction stages, speeding up and facilitating the start-up and operation of priority projects is on the agenda. He said about the construction status of Sadaf Petrochemical Company in the Persian Gulf: By using this plan, we will witness the production of a strategic product in downstream petrochemical industries.

Referring to the 73% progress in the construction of this ESBR production project, he demanded to determine the assignment of feed supply and utility contracts of this petrochemical project and added: so far, more than 9 million and 250 thousand hours of work without incident have been accomplished in this project, and we hope that we will have the same achievements in the future without any incidents.

The Vice President of Planning and Business Development of the Persian Gulf Petrochemical Industries Company further demanded the reopening of the warehouses of the Persian Gulf Holding Petrochemical Complexes in order to provide part of the goods and equipment for this project and continued: with the aim of making the project structure agile, the Petrochemical Industries Development Management Company should be appointed as " Centralized project management" to participate in this plan, which will definitely help the contractor and employer to speed up and facilitate the construction process and start the commissioning process.

The start of Apadana Petrochemical Plant in the Persian Gulf in 1402

Also, on the sidelines of his visit to Apadana Petrochemical company in the Persian Gulf, Neshanzadeh mentioned the 84% progress of this methanol project and said: One of the most important problems facing the construction of plans and projects in the oil and petrochemical industry is managers' postponing making decisions and this is a waste of time and has resulted in delay in the construction and delivery of projects.

He demanded more seriousness from the managers of this petrochemical company to make decisions and determine the tasks of the ongoing measures to complete and operate this project and added: regular and monthly monitoring of this project is on the agenda of the Persian Gulf Petrochemical Industries Company and it is anticipated that the stages of launching and operating this project will be by early March 2023.

The Vice President of Planning and Business Development of the Persian Gulf Petrochemical Company continued to visit the projects under construction in Asalouyeh, pointing to the progress of 86% in the construction of Urea and Ammonia Petrochemical Units, any delay in launching this project will not be tolerated.

Neshanzadeh also called for the pre-commissioning and commissioning of the pipeline and torch facilities, ammonia storage tanks, ammonia export pipeline and preparation of the petrochemical terminal to speed up the process of launching the ammonia petrochemical production unit